Holm Onephoto: holm.aeUnder construction

Holm One

DLD project no. 4181 · Al Satwa

Progress
6.85%
DLD inspected 27 Jul 2026
Handover
~ Mar 2028
Est. finish 30 Mar 2028
Escrow
#0205933054505
Registered escrow account
Google rating
5.0 ★
2 reviews

DLD developer no. 2428 · HOLM AVENUE REAL ESTATE DEVELOPMENT L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
6.85% of construction complete · last inspected by DLD 27 Jul 2026

on pace — ≈22 pts behind the plan as of the last inspection

today
inspected 27 Jul 2026
start 15 Nov 2025 est. finish 30 Mar 2028
Google · this project
5.0
2 reviews

Location

Holm One: common questions

Is Holm One delayed?

Not by DLD figures. Construction was 6.85% complete at the last DLD inspection on 27 July 2026, in line with or ahead of its registered timeline (about 29% expected by then, planned completion 30 March 2028).

When is the handover of Holm One?

The planned completion date registered with Dubai Land Department is 30 March 2028. Handover usually follows completion; the developer confirms the exact date.

How much of Holm One is built?

Construction was 6.85% complete at the last DLD inspection on 27 July 2026, as published by Dubai Land Department.

Where is Holm One located?

Holm One is in Al Satwa, Dubai.

Who is the developer of Holm One?

Holm One is developed by HOLM AVENUE REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 2428). It is registered with Dubai Land Department as project no. 4181.

Does Holm One have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0205933054505. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Holm One?

The most recent sale registered with Dubai Land Department was on 1 October 2026 for AED 1,132,761. Across the 184 recorded sales, the average was AED 2,238 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.