photo: hillsview.aeUnder constructionHills View at Wasl Gate
Developer: Suncrest Hills Property L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 28 Sept 2026 | Sales | Off-plan | Flat · Studio | 42.35 | 456 | 652,000 | 15,396 | 1,430 |
| 28 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 71.91 | 774 | 1,099,928 | 15,296 | 1,421 |
| 21 Sept 2026 | Sales | Off-plan | Flat · Studio | 39.18 | 422 | 738,750 | 18,855 | 1,752 |
| 13 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 73.13 | 787 | 1,057,355 | 14,459 | 1,343 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 72.26 | 778 | 1,044,411 | 14,454 | 1,343 |
| 30 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 72.29 | 778 | 1,091,030 | 15,092 | 1,402 |
| 27 Jul 2026 | Sales | Off-plan | Flat · Studio | 39.37 | 424 | 805,000 | 20,447 | 1,900 |
| 27 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 70.14 | 755 | 1,083,396 | 15,446 | 1,435 |
| 25 Jul 2026 | Sales | Off-plan | Flat · Studio | 39.25 | 422 | 680,678 | 17,342 | 1,611 |
| 15 Jul 2026 | Gifts | Off-plan | Flat · 1 B/R | 72.27 | 778 | 1,107,004.83 | 15,318 | 1,423 |
| 14 Jul 2026 | Gifts | Off-plan | Flat · 1 B/R | 72.27 | 778 | 1,107,004.83 | 15,318 | 1,423 |
| 3 Jul 2026 | Sales | Off-plan | Flat · Studio | 41.77 | 450 | 680,000 | 16,280 | 1,512 |
| 25 Jun 2026 | Sales | Off-plan | Flat · Studio | 39.41 | 424 | 663,026 | 16,824 | 1,563 |
| 25 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 70.11 | 755 | 1,082,937 | 15,446 | 1,435 |
| 25 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 73.11 | 787 | 1,120,663 | 15,328 | 1,424 |
Hills View at Wasl Gate: common questions
Is Hills View at Wasl Gate delayed?
It is behind plan. Construction was 9.05% complete at the last DLD inspection on 24 September 2026, while its registered timeline (planned completion 30 June 2028) would expect about 41% by then.
When is the handover of Hills View at Wasl Gate?
The planned completion date registered with Dubai Land Department is 30 June 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Hills View at Wasl Gate is built?
Construction was 9.05% complete at the last DLD inspection on 24 September 2026, as published by Dubai Land Department.
Where is Hills View at Wasl Gate located?
Hills View at Wasl Gate is in Jabal Ali First, Dubai.
Who is the developer of Hills View at Wasl Gate?
Hills View at Wasl Gate is developed by Suncrest Hills Property L.L.C. It is registered with Dubai Land Department as project no. 3627.
Does Hills View at Wasl Gate have an escrow account?
Yes. Dubai Land Department open data lists escrow account 012119036548. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Hills View at Wasl Gate?
The most recent sale registered with Dubai Land Department was on 28 September 2026 for AED 652,000. Across the 126 recorded sales, the average was AED 1,461 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.