HILLMONT RESIDENCES BY ELLINGTONphoto: ellingtonproperties.aeActive
Progress
26.29%
Handover
~ Dec 2026
Escrow
#13635208920003

HILLMONT RESIDENCES BY ELLINGTON

#3081 · B L G DEVELOPMENT L.L.C · Al Barsha South Fourth · 145 units

declared value 98.0M AED data last checked 12 Sept 2026

Residential Building (UG+G +4P+12F+R) with retail @GF + swimming pool with Gym @ first floor

Construction progress

26.29% of construction complete · last inspected by DLD 22 Jul 2026

≈57 pts behind the planned pace as of the last inspection

today
inspected 22 Jul 2026
start 14 May 2024 est. finish 31 Dec 2026