Haven By Aldar 1photo: aldar.comActive
Progress
44.15%
Handover
~ Nov 2027
Escrow
#4031225788862002

Haven By Aldar 1

#2873 · AURORA SPV 1 L.L.C · Wadi Al Safa 5

data last checked 17 Jul 2026

Construction progress

44.15% of construction complete · last inspected by DLD 28 Jul 2026

on pace — ≈19 pts behind the plan as of the last inspection

today
inspected 28 Jul 2026
start 30 Apr 2024 est. finish 28 Nov 2027