photo: emaar.comUnder constructionDLD developer no. 1211 · EMAAR DEVELOPMENT P.J.S.C.
Data last checked 29 Oct 2026
More from Emaar →Residential development consisting of 37 villas (G+2) and 510 townhouse units (G+1)
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 16 Oct 2026 | Sales | Off-plan | Villa · 3 B/R | 148.72 | 1,601 | 3,100,000 | 20,845 | 1,937 |
| 16 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 244.67 | 2,634 | 3,982,154 | 16,276 | 1,512 |
| 12 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 347.25 | 3,738 | 4,915,888 | 14,157 | 1,315 |
| 11 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 293.22 | 3,156 | 4,763,888 | 16,247 | 1,509 |
| 8 Sept 2026 | Sales | Off-plan | Villa · 3 B/R | 148.72 | 1,601 | 3,646,470 | 24,519 | 2,278 |
| 4 Sept 2026 | Gifts | Ready | Land | 502.54 | 5,409 | 2,839,751.91 | 5,651 | 525 |
| 10 Aug 2026 | Gifts | Off-plan | Villa · 4 B/R | 294.45 | 3,169 | 2,374,518.43 | 8,064 | 749 |
| 16 Jul 2026 | Sales | Off-plan | Villa · 3 B/R | 148.73 | 1,601 | 3,641,888 | 24,487 | 2,275 |
| 14 Jul 2026 | Sales | Ready | Land | 501.69 | 5,400 | 10,959,866 | 21,846 | 2,030 |
| 13 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 274.45 | 2,954 | 4,780,888 | 17,420 | 1,618 |
| 13 Jul 2026 | Sales | Off-plan | Villa · 3 B/R | 148.72 | 1,601 | 3,650,888 | 24,549 | 2,281 |
| 10 Jun 2026 | Sales | Off-plan | Villa · 3 B/R | 148.72 | 1,601 | 3,610,888 | 24,280 | 2,256 |
| 1 Jun 2026 | Sales | Off-plan | Villa · 4 B/R | 350.28 | 3,770 | 4,917,888 | 14,040 | 1,304 |
| 27 Apr 2026 | Sales | Off-plan | Villa · 4 B/R | 258.97 | 2,788 | 4,677,888 | 18,063 | 1,678 |
| 9 Apr 2026 | Sales | Off-plan | Villa · 4 B/R | 275.81 | 2,969 | 4,775,888 | 17,316 | 1,609 |
Grand Polo - Equiterra: common questions
Is Grand Polo - Equiterra delayed?
Not by DLD figures. Construction was 0.83% complete at the last DLD inspection on 14 May 2026, in line with or ahead of its registered timeline (about 5% expected by then, planned completion 31 August 2029).
When is the handover of Grand Polo - Equiterra?
The planned completion date registered with Dubai Land Department is 31 August 2029. Handover usually follows completion; the developer confirms the exact date.
How much of Grand Polo - Equiterra is built?
Construction was 0.83% complete at the last DLD inspection on 14 May 2026, as published by Dubai Land Department.
Where is Grand Polo - Equiterra located?
Grand Polo - Equiterra is in Dubai Investment Park Second, Dubai.
Who is the developer of Grand Polo - Equiterra?
Grand Polo - Equiterra is developed by EMAAR DEVELOPMENT P.J.S.C. (DLD developer no. 1211). It is registered with Dubai Land Department as project no. 4185, with 547 units.
Does Grand Polo - Equiterra have an escrow account?
Yes. Dubai Land Department open data lists escrow account 3538215410321. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Grand Polo - Equiterra?
The most recent sale registered with Dubai Land Department was on 16 October 2026 for AED 3,100,000. Across the 128 recorded sales, the average was AED 1,997 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.