Golf Hillsphoto: emaar.comUnder construction

Golf Hills

DLD project no. 4117 · Madinat Al Mataar

Progress
3.67%
DLD inspected 23 Jun 2026
Handover
~ Sept 2029
Est. finish 30 Sept 2029
Escrow
#9009226131257008
Registered escrow account
Google rating
—

DLD developer no. 1155 · EMAAR DUBAI SOUTH DWC LLC

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Emaar →
DLDConstruction inspection
3.67% of construction complete · last inspected by DLD 23 Jun 2026

on pace — ≈9 pts behind the plan as of the last inspection

today
inspected 23 Jun 2026
start 30 Dec 2025 est. finish 30 Sept 2029

Golf Hills: common questions

Is Golf Hills delayed?

Not by DLD figures. Construction was 3.67% complete at the last DLD inspection on 23 June 2026, in line with or ahead of its registered timeline (about 13% expected by then, planned completion 30 September 2029).

When is the handover of Golf Hills?

The planned completion date registered with Dubai Land Department is 30 September 2029. Handover usually follows completion; the developer confirms the exact date.

How much of Golf Hills is built?

Construction was 3.67% complete at the last DLD inspection on 23 June 2026, as published by Dubai Land Department.

Where is Golf Hills located?

Golf Hills is in Madinat Al Mataar, Dubai.

Who is the developer of Golf Hills?

Golf Hills is developed by EMAAR DUBAI SOUTH DWC LLC (DLD developer no. 1155). It is registered with Dubai Land Department as project no. 4117.

Does Golf Hills have an escrow account?

Yes. Dubai Land Department open data lists escrow account 9009226131257008. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Golf Hills?

The most recent sale registered with Dubai Land Department was on 22 June 2026 for AED 2,074,888. Across the 50 recorded sales, the average was AED 1,712 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.