Golf Dalephoto: emaar.comUnder construction

Golf Dale

DLD project no. 3427 · Madinat Al Mataar

Progress
0.27%
DLD inspected 30 Apr 2026
Handover
~ Dec 2028
Est. finish 31 Dec 2028
Escrow
#11134281920033
Registered escrow account
Google rating
—

DLD developer no. 1155 · EMAAR DUBAI SOUTH DWC LLC

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Emaar →
DLDConstruction inspection
0.27% of construction complete · last inspected by DLD 30 Apr 2026

≈26 pts behind the planned pace as of the last inspection

today
inspected 30 Apr 2026
start 23 May 2025 est. finish 31 Dec 2028

Location

Golf Dale: common questions

Is Golf Dale delayed?

It is behind plan. Construction was 0.27% complete at the last DLD inspection on 30 April 2026, while its registered timeline (planned completion 31 December 2028) would expect about 26% by then.

When is the handover of Golf Dale?

The planned completion date registered with Dubai Land Department is 31 December 2028. Handover usually follows completion; the developer confirms the exact date.

How much of Golf Dale is built?

Construction was 0.27% complete at the last DLD inspection on 30 April 2026, as published by Dubai Land Department.

Where is Golf Dale located?

Golf Dale is in Madinat Al Mataar, Dubai.

Who is the developer of Golf Dale?

Golf Dale is developed by EMAAR DUBAI SOUTH DWC LLC (DLD developer no. 1155). It is registered with Dubai Land Department as project no. 3427.

Does Golf Dale have an escrow account?

Yes. Dubai Land Department open data lists escrow account 11134281920033. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Golf Dale?

The most recent sale registered with Dubai Land Department was on 18 June 2026 for AED 1,792,888. Across the 2 recorded sales, the average was AED 1,596 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.