GARDENS 2photo: imandevelopers.comActive
Progress
68.49%
Handover
Escrow
#0205302400818

GARDENS 2

#2938 · IMAN DEVELOPERS L.L.C · Arjan

More from Iman
data last checked 17 Jul 2026

Construction progress

68.49% of construction complete · last inspected by DLD 16 Dec 2025

≈29 pts behind the planned pace as of the last inspection

today inspected 16 Dec 2025
start 20 Apr 2024 est. finish 30 Dec 2025
Google · this project
4.6
5 reviews