Active
Progress
7.03%
Handover
~ Dec 2027
Escrow
#1001226928732002

Forum 2

#3807 · K X G REAL ESTATE DEVELOPMENT L.L.C · Wadi Al Safa 3 · 77 units

declared value 36.0M AED data last checked 12 Sept 2026

2B+ G+8+R residential

Construction progress

7.03% of construction complete · last inspected by DLD 10 Aug 2026

≈28 pts behind the planned pace as of the last inspection

today
inspected 10 Aug 2026
start 15 Nov 2025 est. finish 15 Dec 2027