photo: hzdevelopment.aeUnder constructionFOREST CITY TOWER 2
DLD developer no. 1124 · AL HELAL AL ZAHABY REAL ESTATE DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 28 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 131.77 | 1,418 | 1,417,616.96 | 10,758 | 999 |
| 19 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 164.03 | 1,766 | 1,731,555.84 | 10,556 | 981 |
| 10 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 129.98 | 1,399 | 1,504,888 | 11,578 | 1,076 |
| 10 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 74.36 | 800 | 695,166 | 9,349 | 869 |
| 1 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 81.1 | 873 | 940,888 | 11,602 | 1,078 |
| 18 Sept 2026 | Sales | Off-plan | Flat · Studio | 42.42 | 457 | 546,249.32 | 12,877 | 1,196 |
| 11 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 164.03 | 1,766 | 1,671,893.6 | 10,193 | 947 |
| 13 Aug 2026 | Sales | Off-plan | Flat · 3 B/R | 164.03 | 1,766 | 1,499,110.4 | 9,139 | 849 |
| 20 Jul 2026 | Sales | Off-plan | Flat · Studio | 60.64 | 653 | 702,888 | 11,591 | 1,077 |
| 2 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 164.03 | 1,766 | 1,725,888 | 10,522 | 978 |
| 5 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 80.45 | 866 | 989,415.84 | 12,299 | 1,143 |
| 22 May 2026 | Sales | Off-plan | Flat · 2 B/R | 129.98 | 1,399 | 1,410,462 | 10,851 | 1,008 |
| 12 May 2026 | Sales | Off-plan | Flat · Studio | 60.64 | 653 | 666,392.53 | 10,989 | 1,021 |
| 12 May 2026 | Sales | Off-plan | Flat · 2 B/R | 129.98 | 1,399 | 1,661,888 | 12,786 | 1,188 |
| 12 May 2026 | Sales | Off-plan | Flat · 3 B/R | 164.03 | 1,766 | 1,683,293.6 | 10,262 | 953 |
FOREST CITY TOWER 2: common questions
Is FOREST CITY TOWER 2 delayed?
It is behind plan. Construction was 1.18% complete at the last DLD inspection on 15 October 2026, while its registered timeline (planned completion 1 June 2027) would expect about 69% by then.
When is the handover of FOREST CITY TOWER 2?
The planned completion date registered with Dubai Land Department is 1 June 2027. Handover usually follows completion; the developer confirms the exact date.
How much of FOREST CITY TOWER 2 is built?
Construction was 1.18% complete at the last DLD inspection on 15 October 2026, as published by Dubai Land Department.
Where is FOREST CITY TOWER 2 located?
FOREST CITY TOWER 2 is in Dubai Land Residence Complex, Dubai.
Who is the developer of FOREST CITY TOWER 2?
FOREST CITY TOWER 2 is developed by AL HELAL AL ZAHABY REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1124). It is registered with Dubai Land Department as project no. 3727.
Does FOREST CITY TOWER 2 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 3717370312516. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in FOREST CITY TOWER 2?
The most recent sale registered with Dubai Land Department was on 28 October 2026 for AED 1,417,617. Across the 45 recorded sales, the average was AED 1,063 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.