Floarea  Grandephoto: mashriqelite.comActive
Progress
48.2%
Handover
~ Aug 2027
Escrow
#019500000724

Floarea Grande

#3494 · MASHRIQ ELITE REAL ESTATE DEVELOPMENT L.L.C · Arjan

data last checked 17 Jul 2026

Construction progress

48.2% of construction complete · last inspected by DLD 14 Aug 2026

on pace — ≈12 pts behind the plan as of the last inspection

today
inspected 14 Aug 2026
start 15 Feb 2025 est. finish 14 Aug 2027
Google · this project
5.0
3 reviews