Expo City Mangrove Residencesphoto: expo-mangrove-residences.comActive
Progress
91.16%
Handover
Escrow
#001582318250401

Expo City Mangrove Residences

#2612 · Expo City Mangrove Residences Development FZCO · Madinat Al Mataar · 470 units

declared value 589.3M AED data last checked 12 Sept 2026

The project is composed of 3B+G+(3) Buildings The Project accommodates - Block (A) 150 Residential units (Ground + 16 + Roof) - Block (B) 155 Residential units (Ground + 16 + Roof) - Block (C) 145 Residential units (Ground + 16) - 20 Commercial Units.

Construction progress

91.16% of construction complete · last inspected by DLD 18 Aug 2026

overdue — planned finish was 31 Jan 2026, still at 91.16%

today
inspected 18 Aug 2026
start 1 Jun 2023 est. finish 31 Jan 2026