EQUITI TOWERphoto: equitiproperties.comActive
Progress
70.2%
Handover
Escrow
#11990610920012

EQUITI TOWER

#3185 · B N H REAL ESTATE DEVELOPER · International City Ph 2 & 3

data last checked 17 Jul 2026

Construction progress

70.2% of construction complete · last inspected by DLD 31 Dec 2025

overdue — planned finish was 30 Aug 2025, still at 70.2%

today
inspected 31 Dec 2025
start 12 Jun 2024 est. finish 30 Aug 2025
Google · this project