photo: enara.omniyat.comUnder constructionDeveloper: Forty Two Downtown Real Estate Developments L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Omniyat →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Aug 2026 | Gifts | Off-plan | Office · NA | 753.48 | 8,110 | 8,000,213.32 | 10,618 | 986 |
| 18 Jun 2026 | Sales | Off-plan | Office · NA | 377.4 | 4,062 | 12,704,540 | 33,663 | 3,127 |
| 18 Jun 2026 | Sales | Off-plan | Office · NA | 491.79 | 5,294 | 13,392,000 | 27,231 | 2,530 |
| 4 Jun 2026 | Sales | Off-plan | Office · NA | 825.5 | 8,886 | 61,418,675 | 74,402 | 6,912 |
| 19 May 2026 | Sales | Off-plan | Office · NA | 377.4 | 4,062 | 25,409,081 | 67,327 | 6,255 |
| 6 Mar 2026 | Sales | Off-plan | Office · NA | 525.13 | 5,652 | 31,470,050 | 59,928 | 5,568 |
| 6 Feb 2026 | Sales | Off-plan | Office · NA | 753.53 | 8,111 | 55,854,141 | 74,123 | 6,886 |
| 6 Feb 2026 | Sales | Off-plan | Office · NA | 228.97 | 2,465 | 18,505,971 | 80,823 | 7,509 |
| 30 Jan 2026 | Sales | Off-plan | Office · NA | 562.06 | 6,050 | 46,261,693 | 82,307 | 7,647 |
| 27 Jan 2026 | Sales | Off-plan | Office · NA | 491.79 | 5,294 | 26,784,000 | 54,462 | 5,060 |
| 23 Jan 2026 | Sales | Off-plan | Office · NA | 413.3 | 4,449 | 33,337,344 | 80,661 | 7,494 |
| 16 Jan 2026 | Sales | Off-plan | Office · NA | 547.66 | 5,895 | 38,587,818 | 70,459 | 6,546 |
| 14 Jan 2026 | Sales | Off-plan | Office · NA | 1,279.06 | 13,768 | 70,380,349 | 55,025 | 5,112 |
| 5 Jan 2026 | Sales | Off-plan | Office · NA | 648.76 | 6,983 | 45,917,403 | 70,777 | 6,575 |
Enara By Omniyat: common questions
Is Enara By Omniyat delayed?
It is behind plan. Construction was 7.25% complete at the last DLD inspection on 12 June 2026, while its registered timeline (planned completion 31 December 2027) would expect about 52% by then.
When is the handover of Enara By Omniyat?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Enara By Omniyat is built?
Construction was 7.25% complete at the last DLD inspection on 12 June 2026, as published by Dubai Land Department.
Where is Enara By Omniyat located?
Enara By Omniyat is in Business Bay, Dubai.
Who is the developer of Enara By Omniyat?
Enara By Omniyat is developed by Forty Two Downtown Real Estate Developments L.L.C. It is registered with Dubai Land Department as project no. 3220.
Does Enara By Omniyat have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019000084172. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Enara By Omniyat?
The most recent sale registered with Dubai Land Department was on 18 June 2026 for AED 12,704,540. Across the 13 recorded sales, the average was AED 5,940 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.