Empire Livingsphoto: empire-livings.comActive
Progress
13.34%
Handover
~ Nov 2027
Escrow
#0205877278404

Empire Livings

#3181 · EMPIRE REAL ESTATE DEVELOPMENTS L.L.C · Dubai Science Park

data last checked 17 Jul 2026

Construction progress

13.34% of construction complete · last inspected by DLD 31 Jul 2026

≈42 pts behind the planned pace as of the last inspection

today
inspected 31 Jul 2026
start 30 Nov 2024 est. finish 30 Nov 2027