photo: empiredevelopments.aeUnder constructionEMPIRE LAKEVIEWS
Developer: Empire Crown Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 22 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 70.03 | 754 | 1,074,777 | 15,347 | 1,426 |
| 22 Oct 2026 | Sales | Off-plan | Flat · Studio | 38.16 | 411 | 849,777 | 22,269 | 2,069 |
| 22 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 79.59 | 857 | 1,424,777 | 17,901 | 1,663 |
| 22 Oct 2026 | Sales | Off-plan | Flat · Studio | 38.67 | 416 | 879,777 | 22,751 | 2,114 |
| 18 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 123.38 | 1,328 | 2,149,777 | 17,424 | 1,619 |
| 18 Sept 2026 | Sales | Off-plan | Flat · Studio | 39.52 | 425 | 704,777 | 17,833 | 1,657 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 73.39 | 790 | 1,349,777 | 18,392 | 1,709 |
| 14 Sept 2026 | Sales | Off-plan | Flat · Studio | 38.44 | 414 | 924,777 | 24,058 | 2,235 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 70.06 | 754 | 1,024,777 | 14,627 | 1,359 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 70.06 | 754 | 1,424,777 | 20,337 | 1,889 |
| 14 Sept 2026 | Sales | Off-plan | Flat · Studio | 38.16 | 411 | 679,777 | 17,814 | 1,655 |
| 5 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 73.39 | 790 | 1,274,777 | 17,370 | 1,614 |
| 5 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 122.6 | 1,320 | 2,150,000 | 17,537 | 1,629 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 121.92 | 1,312 | 2,349,777 | 19,273 | 1,791 |
| 20 Jul 2026 | Sales | Off-plan | Flat · Studio | 38.42 | 414 | 824,777 | 21,467 | 1,994 |
EMPIRE LAKEVIEWS: common questions
Is EMPIRE LAKEVIEWS delayed?
Not by DLD figures. Construction was 2.05% complete at the last DLD inspection on 23 March 2026, in line with or ahead of its registered timeline (about 25% expected by then, planned completion 24 June 2028).
When is the handover of EMPIRE LAKEVIEWS?
The planned completion date registered with Dubai Land Department is 24 June 2028. Handover usually follows completion; the developer confirms the exact date.
How much of EMPIRE LAKEVIEWS is built?
Construction was 2.05% complete at the last DLD inspection on 23 March 2026, as published by Dubai Land Department.
Where is EMPIRE LAKEVIEWS located?
EMPIRE LAKEVIEWS is in Liwan, Dubai.
Who is the developer of EMPIRE LAKEVIEWS?
EMPIRE LAKEVIEWS is developed by Empire Crown Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3357.
Does EMPIRE LAKEVIEWS have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205902532504. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in EMPIRE LAKEVIEWS?
The most recent sale registered with Dubai Land Department was on 22 October 2026 for AED 1,074,777. Across the 110 recorded sales, the average was AED 1,709 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.