photo: deyaar.aeUnder constructionDLD developer no. 15 · DEYAAR DEVELOPMENT (P.J.S.C)
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Deyaar →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 7 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 165.12 | 1,777 | 2,262,031 | 13,699 | 1,273 |
| 7 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 165.11 | 1,777 | 2,379,469 | 14,411 | 1,339 |
| 7 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 189.98 | 2,045 | 2,342,518 | 12,330 | 1,146 |
| 2 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 165.12 | 1,777 | 2,361,793 | 14,303 | 1,329 |
| 2 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 165.12 | 1,777 | 2,344,070 | 14,196 | 1,319 |
| 2 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 76.67 | 825 | 1,120,722 | 14,617 | 1,358 |
| 2 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 165.12 | 1,777 | 2,370,655 | 14,357 | 1,334 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 130.99 | 1,410 | 1,572,363 | 12,004 | 1,115 |
| 13 Jul 2026 | Gifts | Off-plan | Flat · 2 B/R | 106.75 | 1,149 | 675,066.91 | 6,324 | 588 |
| 17 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 75.88 | 817 | 1,176,068 | 15,499 | 1,440 |
| 16 Jun 2026 | Sales | Off-plan | Flat · 3 B/R | 165.12 | 1,777 | 2,255,574 | 13,660 | 1,269 |
| 12 May 2026 | Sales | Off-plan | Flat · 1 B/R | 64.02 | 689 | 932,371 | 14,564 | 1,353 |
| 11 May 2026 | Sales | Off-plan | Flat · 1 B/R | 76.56 | 824 | 1,075,173 | 14,044 | 1,305 |
| 11 May 2026 | Sales | Off-plan | Flat · 1 B/R | 75.2 | 809 | 1,056,204 | 14,045 | 1,305 |
| 20 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 63.84 | 687 | 943,323 | 14,776 | 1,373 |
EMBER AT PARK FIVE: common questions
Is EMBER AT PARK FIVE delayed?
It is behind plan. Construction was 18.24% complete at the last DLD inspection on 17 September 2026, while its registered timeline (planned completion 1 June 2027) would expect about 68% by then.
When is the handover of EMBER AT PARK FIVE?
The planned completion date registered with Dubai Land Department is 1 June 2027. Handover usually follows completion; the developer confirms the exact date.
How much of EMBER AT PARK FIVE is built?
Construction was 18.24% complete at the last DLD inspection on 17 September 2026, as published by Dubai Land Department.
Where is EMBER AT PARK FIVE located?
EMBER AT PARK FIVE is in Dubai Production City, Dubai.
Who is the developer of EMBER AT PARK FIVE?
EMBER AT PARK FIVE is developed by DEYAAR DEVELOPMENT (P.J.S.C) (DLD developer no. 15). It is registered with Dubai Land Department as project no. 3344.
Does EMBER AT PARK FIVE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582143761201. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in EMBER AT PARK FIVE?
The most recent sale registered with Dubai Land Department was on 7 September 2026 for AED 2,262,031. Across the 86 recorded sales, the average was AED 1,339 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.