photo: ellingtonproperties.aeUnder constructionDLD developer no. 2371 · ELLINGTON PCFC DEVELOPERS L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Ellington →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 28 Oct 2026 | Gifts | Off-plan | Flat · 2 B/R | 127.19 | 1,369 | 3,500,001.89 | 27,518 | 2,556 |
| 26 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 116.22 | 1,251 | 3,497,828 | 30,097 | 2,796 |
| 20 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 116.19 | 1,251 | 3,143,828 | 27,058 | 2,514 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 127.19 | 1,369 | 3,300,828 | 25,952 | 2,411 |
| 29 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 76.22 | 820 | 2,097,828 | 27,523 | 2,557 |
| 22 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 116.22 | 1,251 | 3,190,828 | 27,455 | 2,551 |
| 2 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 127.2 | 1,369 | 3,679,828 | 28,929 | 2,688 |
| 20 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 114.97 | 1,238 | 3,137,828 | 27,293 | 2,536 |
| 29 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 78.44 | 844 | 2,050,828 | 26,145 | 2,429 |
| 29 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 76.75 | 826 | 2,057,828 | 26,812 | 2,491 |
| 23 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 76.34 | 822 | 2,034,828 | 26,655 | 2,476 |
| 16 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 152.46 | 1,641 | 4,061,828 | 26,642 | 2,475 |
| 16 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 180.95 | 1,948 | 4,547,828 | 25,133 | 2,335 |
| 5 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 114.97 | 1,238 | 3,286,828 | 28,589 | 2,656 |
| 4 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 78.44 | 844 | 2,007,828 | 25,597 | 2,378 |
ELTIERA HEIGHTS: common questions
Is ELTIERA HEIGHTS delayed?
It is behind plan. Construction was 3.01% complete at the last DLD inspection on 20 July 2026, while its registered timeline (planned completion 31 December 2028) would expect about 31% by then.
When is the handover of ELTIERA HEIGHTS?
The planned completion date registered with Dubai Land Department is 31 December 2028. Handover usually follows completion; the developer confirms the exact date.
How much of ELTIERA HEIGHTS is built?
Construction was 3.01% complete at the last DLD inspection on 20 July 2026, as published by Dubai Land Department.
Where is ELTIERA HEIGHTS located?
ELTIERA HEIGHTS is in Jumeirah Heights, Dubai.
Who is the developer of ELTIERA HEIGHTS?
ELTIERA HEIGHTS is developed by ELLINGTON PCFC DEVELOPERS L.L.C (DLD developer no. 2371). It is registered with Dubai Land Department as project no. 3852.
Does ELTIERA HEIGHTS have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0323600623002. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in ELTIERA HEIGHTS?
The most recent sale registered with Dubai Land Department was on 26 October 2026 for AED 3,497,828. Across the 72 recorded sales, the average was AED 2,562 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.