photo: deyaar.aeUnder constructionDLD developer no. 15 · DEYAAR DEVELOPMENT (P.J.S.C)
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Deyaar →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 75.75 | 815 | 1,158,616 | 15,295 | 1,421 |
| 26 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 63.77 | 686 | 935,000 | 14,662 | 1,362 |
| 14 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 76.42 | 823 | 1,091,387 | 14,281 | 1,327 |
| 14 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 114.33 | 1,231 | 1,510,000 | 13,207 | 1,227 |
| 29 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 114.61 | 1,234 | 1,500,000 | 13,088 | 1,216 |
| 23 Jul 2026 | Sales | Off-plan | Flat · Studio | 40.89 | 440 | 684,286 | 16,735 | 1,555 |
| 24 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 75.08 | 808 | 1,152,043 | 15,344 | 1,426 |
| 23 Jun 2026 | Sales | Off-plan | Flat · Studio | 41.07 | 442 | 634,789 | 15,456 | 1,436 |
| 19 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 108.08 | 1,163 | 1,205,872 | 11,157 | 1,037 |
| 19 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 84.96 | 915 | 998,274 | 11,750 | 1,092 |
| 29 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 103.28 | 1,112 | 1,194,007 | 11,561 | 1,074 |
| 16 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 76.44 | 823 | 1,071,743 | 14,021 | 1,303 |
| 7 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 72.4 | 779 | 1,018,359 | 14,066 | 1,307 |
| 7 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 76.42 | 823 | 1,096,507 | 14,348 | 1,333 |
| 3 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 75.42 | 812 | 1,153,636 | 15,296 | 1,421 |
ELM AT PARK FIVE: common questions
Is ELM AT PARK FIVE delayed?
It is behind plan. Construction was 6.28% complete at the last DLD inspection on 17 September 2026, while its registered timeline (planned completion 31 December 2027) would expect about 41% by then.
When is the handover of ELM AT PARK FIVE?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of ELM AT PARK FIVE is built?
Construction was 6.28% complete at the last DLD inspection on 17 September 2026, as published by Dubai Land Department.
Where is ELM AT PARK FIVE located?
ELM AT PARK FIVE is in Dubai Production City, Dubai.
Who is the developer of ELM AT PARK FIVE?
ELM AT PARK FIVE is developed by DEYAAR DEVELOPMENT (P.J.S.C) (DLD developer no. 15). It is registered with Dubai Land Department as project no. 4051.
Does ELM AT PARK FIVE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 454761830009. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in ELM AT PARK FIVE?
The most recent sale registered with Dubai Land Department was on 26 August 2026 for AED 1,158,616. Across the 85 recorded sales, the average was AED 1,326 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.