Elirephoto: qbd.aeUnder construction

Elire

DLD project no. 3467 · Business Bay

Progress
8.15%
DLD inspected 11 Aug 2026
Handover
~ Dec 2028
Est. finish 15 Dec 2028
Escrow
#1091006021279010
Registered escrow account
Google rating
5.0 ★
2 reviews

DLD developer no. 1692 · QUBE DEVELOPMENT L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
8.15% of construction complete · last inspected by DLD 11 Aug 2026

≈28 pts behind the planned pace as of the last inspection

today
inspected 11 Aug 2026
start 15 Apr 2025 est. finish 15 Dec 2028
Google · this project
5.0
2 reviews

Location

Elire: common questions

Is Elire delayed?

It is behind plan. Construction was 8.15% complete at the last DLD inspection on 11 August 2026, while its registered timeline (planned completion 15 December 2028) would expect about 36% by then.

When is the handover of Elire?

The planned completion date registered with Dubai Land Department is 15 December 2028. Handover usually follows completion; the developer confirms the exact date.

How much of Elire is built?

Construction was 8.15% complete at the last DLD inspection on 11 August 2026, as published by Dubai Land Department.

Where is Elire located?

Elire is in Business Bay, Dubai.

Who is the developer of Elire?

Elire is developed by QUBE DEVELOPMENT L.L.C (DLD developer no. 1692). It is registered with Dubai Land Department as project no. 3467.

Does Elire have an escrow account?

Yes. Dubai Land Department open data lists escrow account 1091006021279010. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Elire?

The most recent sale registered with Dubai Land Department was on 19 February 2026 for AED 2,792,589. Across the 1 recorded sales, the average was AED 4,265 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.