photo: edgewater-residences.aeUnder constructionEdgewater Residences 3
DLD developer no. 1624 · M G S DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Aug 2026
(G+2P) (Wing A(12F+R) +Wing B (12F+R) +Wing C ( 12F +R) with Swimming pool, Gym & landscape @First floor
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 10 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 78.61 | 846 | 2,236,354 | 28,449 | 2,643 |
| 8 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 73.03 | 786 | 2,275,880 | 31,164 | 2,895 |
| 16 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 73.03 | 786 | 2,227,458 | 30,501 | 2,834 |
| 3 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 117.16 | 1,261 | 2,999,543 | 25,602 | 2,379 |
| 8 May 2026 | Sales | Off-plan | Flat · 1 B/R | 73.3 | 789 | 2,235,692 | 30,501 | 2,834 |
| 28 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 78.61 | 846 | 2,238,914 | 28,481 | 2,646 |
| 14 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 73.07 | 787 | 2,199,608 | 30,103 | 2,797 |
| 10 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 73.9 | 795 | 2,232,255 | 30,206 | 2,806 |
| 31 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 78.83 | 849 | 2,234,488 | 28,346 | 2,633 |
| 27 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 78.61 | 846 | 2,227,996 | 28,342 | 2,633 |
| 27 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 73.32 | 789 | 2,282,532 | 31,131 | 2,892 |
| 23 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 73.3 | 789 | 2,187,091 | 29,838 | 2,772 |
| 23 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 73.3 | 789 | 2,232,380 | 30,455 | 2,829 |
| 21 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 73.79 | 794 | 2,268,207 | 30,739 | 2,856 |
| 3 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 72.8 | 784 | 2,191,480 | 30,103 | 2,797 |
Edgewater Residences 3: common questions
Is Edgewater Residences 3 delayed?
It is behind plan. Construction was 15.01% complete at the last DLD inspection on 4 May 2026, while its registered timeline (planned completion 31 January 2027) would expect about 66% by then.
When is the handover of Edgewater Residences 3?
The planned completion date registered with Dubai Land Department is 31 January 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Edgewater Residences 3 is built?
Construction was 15.01% complete at the last DLD inspection on 4 May 2026, as published by Dubai Land Department.
Where is Edgewater Residences 3 located?
Edgewater Residences 3 is in Palm Deira, Dubai.
Who is the developer of Edgewater Residences 3?
Edgewater Residences 3 is developed by M G S DEVELOPMENT L.L.C (DLD developer no. 1624). It is registered with Dubai Land Department as project no. 3177, with 328 units.
Does Edgewater Residences 3 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 13038714920008. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Edgewater Residences 3?
The most recent sale registered with Dubai Land Department was on 10 September 2026 for AED 2,236,354. Across the 28 recorded sales, the average was AED 2,775 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.