photo: dohotels.aeDelayed 9 mo.DO Residences
Developer: One International Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 28 Sept 2026 | Sales | Off-plan | Hotel Apartment · 1 B/R | 79.41 | 855 | 2,664,000 | 33,547 | 3,117 |
| 22 Sept 2026 | Sales | Off-plan | Hotel Apartment · Studio | 39.85 | 429 | 1,182,000 | 29,661 | 2,756 |
| 22 Sept 2026 | Sales | Off-plan | Hotel Apartment · Studio | 40.85 | 440 | 1,600,000 | 39,168 | 3,639 |
| 22 Sept 2026 | Sales | Off-plan | Hotel Apartment · 2 B/R | 120.47 | 1,297 | 4,100,000 | 34,033 | 3,162 |
| 21 Sept 2026 | Sales | Off-plan | Hotel Apartment · 1 B/R | 79.5 | 856 | 2,790,000 | 35,094 | 3,260 |
| 21 Sept 2026 | Sales | Off-plan | Hotel Apartment · 1 B/R | 78.87 | 849 | 2,488,000 | 31,546 | 2,931 |
| 15 Jul 2026 | Sales | Off-plan | Hotel Apartment · Studio | 38.82 | 418 | 1,055,000 | 27,177 | 2,525 |
| 10 Jul 2026 | Sales | Off-plan | Hotel Apartment · 1 B/R | 80.57 | 867 | 2,738,400 | 33,988 | 3,158 |
| 29 Jun 2026 | Sales | Off-plan | Hotel Apartment · 1 B/R | 79.3 | 854 | 2,623,460 | 33,083 | 3,073 |
| 17 Jun 2026 | Sales | Off-plan | Hotel Apartment · Studio | 40.1 | 432 | 1,200,000 | 29,925 | 2,780 |
| 28 Apr 2026 | Sales | Off-plan | Hotel Apartment · 1 B/R | 78.87 | 849 | 2,646,000 | 33,549 | 3,117 |
| 28 Apr 2026 | Sales | Off-plan | Hotel Apartment · Studio | 40.59 | 437 | 1,173,000 | 28,899 | 2,685 |
| 28 Apr 2026 | Sales | Off-plan | Hotel Apartment · Studio | 39.83 | 429 | 1,147,000 | 28,797 | 2,675 |
| 20 Apr 2026 | Sales | Off-plan | Hotel Apartment · Studio | 42.33 | 456 | 1,186,780 | 28,036 | 2,605 |
| 16 Apr 2026 | Sales | Off-plan | Hotel Apartment · Studio | 41.18 | 443 | 1,222,000 | 29,675 | 2,757 |
DO Residences: common questions
Is DO Residences delayed?
Yes. Its planned completion date registered with Dubai Land Department was 31 December 2025, and at the last DLD inspection on 2 October 2026 construction was 1.66% complete.
When is the handover of DO Residences?
The planned completion date registered with Dubai Land Department is 31 December 2025. That date has passed and construction is still under way, so confirm the current schedule with the developer.
How much of DO Residences is built?
Construction was 1.66% complete at the last DLD inspection on 2 October 2026, as published by Dubai Land Department.
Where is DO Residences located?
DO Residences is in Palm Deira, Dubai.
Who is the developer of DO Residences?
DO Residences is developed by One International Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3804.
Does DO Residences have an escrow account?
Yes. Dubai Land Department open data lists escrow account 7771225999852022. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in DO Residences?
The most recent sale registered with Dubai Land Department was on 28 September 2026 for AED 2,664,000. Across the 24 recorded sales, the average was AED 2,871 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.