DAMAC LAGOONS - VENICE (1)photo: damacproperties.comActive
Progress
74.43%
Handover
Escrow
#0205789887419

DAMAC LAGOONS - VENICE (1)

#2396 · ISLAND OASIS PROPERTIES · Al Hebiah Fifth

More from Damac
data last checked 17 Jul 2026

Construction progress

74.43% of construction complete · last inspected by DLD 17 Jul 2026

overdue — planned finish was 29 Sept 2025, still at 74.43%

today
inspected 17 Jul 2026
start 28 Dec 2022 est. finish 29 Sept 2025