DAMAC LAGOONS - MONTE CARLOphoto: damacproperties.comActive
Progress
86.38%
Handover
Escrow
#0205789887421

DAMAC LAGOONS - MONTE CARLO

#2488 · ISLAND OASIS PROPERTIES · Al Hebiah Fifth

More from Damac
data last checked 17 Jul 2026

Construction progress

86.38% of construction complete · last inspected by DLD 9 Jul 2026

overdue — planned finish was 31 Dec 2025, still at 86.38%

today
inspected 9 Jul 2026
start 12 Feb 2022 est. finish 31 Dec 2025