Progress
74.86%
Handover
Escrow
#0205789887427

DAMAC LAGOONS - IBIZA

#2486 · ISLAND OASIS PROPERTIES · Al Hebiah Fifth

More from Damac
data last checked 17 Jul 2026

Construction progress

74.86% of construction complete · last inspected by DLD 10 Jul 2026

overdue — planned finish was 31 Dec 2025, still at 74.86%

today
inspected 10 Jul 2026
start 12 Feb 2022 est. finish 31 Dec 2025