photo: damacproperties.comUnder constructionDLD developer no. 2035 · DAMAC ELITE INVESTMENT CO. L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Damac →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 5 Oct 2026 | Sales | Ready | Land | 144 | 1,550 | 2,988,000 | 20,750 | 1,928 |
| 5 Oct 2026 | Sales | Ready | Land | 144 | 1,550 | 2,988,000 | 20,750 | 1,928 |
| 25 Sept 2026 | Sales | Ready | Land | 144 | 1,550 | 2,330,000 | 16,181 | 1,503 |
| 22 Sept 2026 | Sales | Ready | Land | 144 | 1,550 | 2,330,000 | 16,181 | 1,503 |
| 21 Sept 2026 | Sales | Ready | Land | 219.6 | 2,364 | 2,850,000 | 12,978 | 1,206 |
| 16 Sept 2026 | Sales | Ready | Land | 227.63 | 2,450 | 3,776,600 | 16,591 | 1,541 |
| 21 Aug 2026 | Sales | Ready | Land | 219.6 | 2,364 | 3,840,960 | 17,491 | 1,625 |
| 19 Aug 2026 | Sales | Ready | Land | 144 | 1,550 | 2,988,000 | 20,750 | 1,928 |
| 19 Aug 2026 | Sales | Ready | Land | 144 | 1,550 | 2,748,960 | 19,090 | 1,774 |
| 19 Aug 2026 | Sales | Ready | Land | 219.6 | 2,364 | 4,001,000 | 18,219 | 1,693 |
| 6 Aug 2026 | Sales | Ready | Land | 232.24 | 2,500 | 2,925,000 | 12,595 | 1,170 |
| 6 Aug 2026 | Sales | Ready | Land | 144 | 1,550 | 2,988,000 | 20,750 | 1,928 |
| 3 Aug 2026 | Gifts | Ready | Land | 144 | 1,550 | 2,400,016.84 | 16,667 | 1,548 |
| 29 Jul 2026 | Sales | Ready | Land | 219.6 | 2,364 | 3,840,960 | 17,491 | 1,625 |
| 1 Jul 2026 | Sales | Ready | Land | 144 | 1,550 | 2,988,000 | 20,750 | 1,928 |
DAMAC ISLANDS - FIJI 2: common questions
Is DAMAC ISLANDS - FIJI 2 delayed?
It is behind plan. Construction was 2.15% complete at the last DLD inspection on 1 May 2026, while its registered timeline (planned completion 31 December 2028) would expect about 28% by then.
When is the handover of DAMAC ISLANDS - FIJI 2?
The planned completion date registered with Dubai Land Department is 31 December 2028. Handover usually follows completion; the developer confirms the exact date.
How much of DAMAC ISLANDS - FIJI 2 is built?
Construction was 2.15% complete at the last DLD inspection on 1 May 2026, as published by Dubai Land Department.
Where is DAMAC ISLANDS - FIJI 2 located?
DAMAC ISLANDS - FIJI 2 is in Al Yelayiss 1, Dubai.
Who is the developer of DAMAC ISLANDS - FIJI 2?
DAMAC ISLANDS - FIJI 2 is developed by DAMAC ELITE INVESTMENT CO. L.L.C (DLD developer no. 2035). It is registered with Dubai Land Department as project no. 3507.
Does DAMAC ISLANDS - FIJI 2 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205892602931. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in DAMAC ISLANDS - FIJI 2?
The most recent sale registered with Dubai Land Department was on 5 October 2026 for AED 2,988,000. Across the 44 recorded sales, the average was AED 1,762 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.