photo: damacproperties.comUnder constructionDLD developer no. 2035 · DAMAC ELITE INVESTMENT CO. L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Damac →No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 21 Sept 2026 | Sales | Ready | Land | 453.61 | 4,883 | 6,400,000 | 14,109 | 1,311 |
| 26 Aug 2026 | Sales | Ready | Land | 316.19 | 3,403 | 4,131,600 | 13,067 | 1,214 |
| 17 Jul 2026 | Sales | Ready | Land | 266.61 | 2,870 | 3,953,840 | 14,830 | 1,378 |
| 20 May 2026 | Sales | Ready | Land | 454.42 | 4,891 | 7,990,000 | 17,583 | 1,634 |
| 13 Apr 2026 | Sales | Ready | Land | 450 | 4,844 | 7,971,000 | 17,713 | 1,646 |
| 10 Feb 2026 | Sales | Ready | Land | 144.02 | 1,550 | 380,850 | 2,644 | 246 |
DAMAC ISLANDS - BORA BORA 4: common questions
Is DAMAC ISLANDS - BORA BORA 4 delayed?
It is behind plan. Construction was 2.11% complete at the last DLD inspection on 4 May 2026, while its registered timeline (planned completion 31 December 2028) would expect about 28% by then.
When is the handover of DAMAC ISLANDS - BORA BORA 4?
The planned completion date registered with Dubai Land Department is 31 December 2028. Handover usually follows completion; the developer confirms the exact date.
How much of DAMAC ISLANDS - BORA BORA 4 is built?
Construction was 2.11% complete at the last DLD inspection on 4 May 2026, as published by Dubai Land Department.
Where is DAMAC ISLANDS - BORA BORA 4 located?
DAMAC ISLANDS - BORA BORA 4 is in Al Yelayiss 1, Dubai.
Who is the developer of DAMAC ISLANDS - BORA BORA 4?
DAMAC ISLANDS - BORA BORA 4 is developed by DAMAC ELITE INVESTMENT CO. L.L.C (DLD developer no. 2035). It is registered with Dubai Land Department as project no. 3476.
Does DAMAC ISLANDS - BORA BORA 4 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205892602925. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in DAMAC ISLANDS - BORA BORA 4?
The most recent sale registered with Dubai Land Department was on 21 September 2026 for AED 6,400,000. Across the 6 recorded sales, the average was AED 1,238 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.
