DLD developer no. 2464 · DAMAC PRIME DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
More from Damac →Project consists of 469 Nos. of G+1& G+2 Townhouses and Villas located in Al Yelayis 1, Dubai. The units are designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Sales | Off-plan | Villa · 5 B/R | 219.6 | 2,364 | 3,764,160 | 17,141 | 1,592 |
| 26 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 144.02 | 1,550 | 2,862,358 | 19,875 | 1,846 |
| 26 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 144.02 | 1,550 | 2,862,358 | 19,875 | 1,846 |
| 26 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 144.05 | 1,551 | 2,862,358 | 19,871 | 1,846 |
| 21 Oct 2026 | Sales | Off-plan | Villa · 5 B/R | 144.02 | 1,550 | 3,958,650 | 27,487 | 2,554 |
| 12 Oct 2026 | Sales | Off-plan | Villa · 5 B/R | 219.6 | 2,364 | 3,607,320 | 16,427 | 1,526 |
| 7 Oct 2026 | Sales | Off-plan | Villa · 5 B/R | 226.28 | 2,436 | 3,885,020 | 17,169 | 1,595 |
| 2 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 144 | 1,550 | 2,874,240 | 19,960 | 1,854 |
| 1 Oct 2026 | Sales | Ready | Land | 524.85 | 5,649 | 11,352,000 | 21,629 | 2,009 |
| 18 Sept 2026 | Sales | Off-plan | Villa · 5 B/R | 219.6 | 2,364 | 3,921,000 | 17,855 | 1,659 |
| 17 Sept 2026 | Sales | Off-plan | Villa · 5 B/R | 223.94 | 2,410 | 4,503,360 | 20,110 | 1,868 |
| 15 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 144 | 1,550 | 2,874,240 | 19,960 | 1,854 |
| 3 Sept 2026 | Sales | Off-plan | Villa · 5 B/R | 219.59 | 2,364 | 3,764,160 | 17,142 | 1,593 |
| 1 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 144 | 1,550 | 2,982,000 | 20,708 | 1,924 |
| 1 Sept 2026 | Sales | Off-plan | Villa · 5 B/R | 144 | 1,550 | 3,334,240 | 23,154 | 2,151 |
DAMAC ISLANDS 2 - BERMUDA: common questions
Is DAMAC ISLANDS 2 - BERMUDA delayed?
Not by DLD figures. Construction was 0.22% complete at the last DLD inspection on 11 June 2026, in line with or ahead of its registered timeline (about 3% expected by then, planned completion 30 June 2030).
When is the handover of DAMAC ISLANDS 2 - BERMUDA?
The planned completion date registered with Dubai Land Department is 30 June 2030. Handover usually follows completion; the developer confirms the exact date.
How much of DAMAC ISLANDS 2 - BERMUDA is built?
Construction was 0.22% complete at the last DLD inspection on 11 June 2026, as published by Dubai Land Department.
Where is DAMAC ISLANDS 2 - BERMUDA located?
DAMAC ISLANDS 2 - BERMUDA is in Al Yelayiss 1, Dubai.
Who is the developer of DAMAC ISLANDS 2 - BERMUDA?
DAMAC ISLANDS 2 - BERMUDA is developed by DAMAC PRIME DEVELOPMENT L.L.C (DLD developer no. 2464). It is registered with Dubai Land Department as project no. 4291, with 469 units.
Does DAMAC ISLANDS 2 - BERMUDA have an escrow account?
Yes. Dubai Land Department open data lists escrow account 4031227003608006. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in DAMAC ISLANDS 2 - BERMUDA?
The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 3,764,160. Across the 410 recorded sales, the average was AED 1,820 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.