DAMAC CITYphoto: damacproperties.comActive
Progress
68.66%
Handover
Escrow
#0205799098902

DAMAC CITY

#2374 · J A Parks L.L.C · Dubai Water Canal

More from Damac
data last checked 17 Jul 2026

Construction progress

68.66% of construction complete · last inspected by DLD 15 Jul 2026

overdue — planned finish was 30 Dec 2025, still at 68.66%

today
inspected 15 Jul 2026
start 1 Jun 2022 est. finish 30 Dec 2025
Google · this project
4.2
13 reviews