D1Handed over

D1

DLD project no. 623 · Jaddaf Waterfront

Progress
100%
DLD inspected 21 Dec 2014
Handover
Completed
100% at DLD inspection Dec 2014
Escrow
#0204729153901
Registered escrow account
Google rating
4.5 ★
10 reviews

Developer: Emirates D1 Limited

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
100% of construction complete · last inspected by DLD 21 Dec 2014
inspected 21 Dec 2014
start 1 Dec 2006 est. finish 8 Jun 2015
Google · this project
4.5
10 reviews

Location

D1: common questions

Is D1 delayed?

No. Dubai Land Department lists D1 as finished, so construction is complete.

When is the handover of D1?

D1 is finished. Its planned completion date registered with Dubai Land Department was 8 June 2015.

Where is D1 located?

D1 is in Jaddaf Waterfront, Dubai.

Who is the developer of D1?

D1 is developed by Emirates D1 Limited. It is registered with Dubai Land Department as project no. 623.

Does D1 have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0204729153901. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in D1?

The most recent sale registered with Dubai Land Department was on 15 October 2026 for AED 4,500,000. Across the 23 recorded sales, the average was AED 1,755 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.