photo: wadan.aeUnder constructionCybele By Wadan
DLD developer no. 2166 · WADAN REAL ESTATE DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 25 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 116.79 | 1,257 | 1,382,368.24 | 11,836 | 1,100 |
| 14 Sept 2026 | Sales | Off-plan | Flat · Studio | 41.58 | 448 | 686,956.3 | 16,521 | 1,535 |
| 14 Sept 2026 | Sales | Off-plan | Flat · Studio | 62.38 | 671 | 891,825.9 | 14,297 | 1,328 |
| 10 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 73.53 | 791 | 1,040,446.54 | 14,150 | 1,315 |
| 25 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 118.45 | 1,275 | 2,010,000 | 16,969 | 1,576 |
| 24 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 124.13 | 1,336 | 1,619,260 | 13,045 | 1,212 |
| 23 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 78.84 | 849 | 1,072,464.01 | 13,603 | 1,264 |
| 23 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 109.1 | 1,174 | 1,625,814.75 | 14,902 | 1,384 |
| 21 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 78.84 | 849 | 1,019,695.04 | 12,934 | 1,202 |
| 13 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 124.13 | 1,336 | 1,602,742.96 | 12,912 | 1,200 |
| 27 Jun 2026 | Sales | Off-plan | Flat · Studio | 39.85 | 429 | 501,918.44 | 12,595 | 1,170 |
| 24 Jun 2026 | Sales | Off-plan | Flat · Studio | 39.81 | 429 | 586,335.2 | 14,728 | 1,368 |
| 23 Jun 2026 | Sales | Off-plan | Flat · Studio | 41.58 | 448 | 688,678 | 16,563 | 1,539 |
| 23 Jun 2026 | Sales | Off-plan | Flat · Studio | 41.61 | 448 | 574,464.88 | 13,806 | 1,283 |
| 23 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 118.45 | 1,275 | 1,628,531 | 13,749 | 1,277 |
Cybele By Wadan: common questions
Is Cybele By Wadan delayed?
It is behind plan. Construction was 2.03% complete at the last DLD inspection on 27 July 2026, while its registered timeline (planned completion 30 December 2027) would expect about 29% by then.
When is the handover of Cybele By Wadan?
The planned completion date registered with Dubai Land Department is 30 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Cybele By Wadan is built?
Construction was 2.03% complete at the last DLD inspection on 27 July 2026, as published by Dubai Land Department.
Where is Cybele By Wadan located?
Cybele By Wadan is in Dubai Land Residence Complex, Dubai.
Who is the developer of Cybele By Wadan?
Cybele By Wadan is developed by WADAN REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 2166). It is registered with Dubai Land Department as project no. 4222.
Does Cybele By Wadan have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1011226909082007. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Cybele By Wadan?
The most recent sale registered with Dubai Land Department was on 25 September 2026 for AED 1,382,368. Across the 224 recorded sales, the average was AED 1,412 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.