photo: merathdevelopment.comDelayed 1 mo.Cresswell Plaza
DLD developer no. 2475 · ESSA BOKHOWA PROPERTIES L.L.C
Data last checked 29 Oct 2026
G+4
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 79.52 | 856 | 1,130,000 | 14,210 | 1,320 |
| 22 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 129.08 | 1,389 | 2,026,000 | 15,696 | 1,458 |
| 7 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 119.87 | 1,290 | 1,620,000 | 13,515 | 1,256 |
| 22 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 126.26 | 1,359 | 1,650,000 | 13,068 | 1,214 |
| 14 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 74.97 | 807 | 1,050,000 | 14,006 | 1,301 |
| 13 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 119.53 | 1,287 | 1,580,000 | 13,218 | 1,228 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 123.76 | 1,332 | 1,580,000 | 12,767 | 1,186 |
| 31 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 79.52 | 856 | 1,080,000 | 13,581 | 1,262 |
| 31 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 74.97 | 807 | 1,025,000 | 13,672 | 1,270 |
| 17 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 74.57 | 803 | 990,000 | 13,276 | 1,233 |
| 13 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 119.9 | 1,291 | 1,550,000 | 12,927 | 1,201 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 74.57 | 803 | 1,040,000 | 13,947 | 1,296 |
| 26 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.57 | 803 | 990,000 | 13,276 | 1,233 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.66 | 804 | 1,070,000 | 14,332 | 1,331 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.97 | 807 | 990,000 | 13,205 | 1,227 |
Cresswell Plaza: common questions
Is Cresswell Plaza delayed?
It is behind plan. Construction was 60.09% complete at the last DLD inspection on 20 July 2026, while its registered timeline (planned completion 28 September 2026) would expect about 86% by then.
When is the handover of Cresswell Plaza?
The planned completion date registered with Dubai Land Department is 28 September 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Cresswell Plaza is built?
Construction was 60.09% complete at the last DLD inspection on 20 July 2026, as published by Dubai Land Department.
Where is Cresswell Plaza located?
Cresswell Plaza is in Dubai South, Dubai. Dubai Land Department records it under the Madinat Al Mataar area.
Who is the developer of Cresswell Plaza?
Cresswell Plaza is developed by ESSA BOKHOWA PROPERTIES L.L.C (DLD developer no. 2475). It is registered with Dubai Land Department as project no. 4359, with 35 units.
Does Cresswell Plaza have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019500000874. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Cresswell Plaza?
The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 1,130,000. Across the 26 recorded sales, the average was AED 1,271 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.