Creek Waters 2photo: emaar.comActive
Progress
81.84%
Handover
~ Dec 2027
Escrow
#4031223832785008

Creek Waters 2

#2634 · THE LAGOONS PHASE ONE L.L.C · Dubai Creek Harbour

More from Emaar
data last checked 17 Jul 2026

Construction progress

81.84% of construction complete · last inspected by DLD 31 Jul 2026

on pace with the planned timeline

today
inspected 31 Jul 2026
start 22 Aug 2023 est. finish 31 Dec 2027