Coventry Residencephoto: gfsdevelopments.aeActive
Progress
0%
Handover
~ Nov 2027
Escrow
#19505233

Coventry Residence

#4022 · G F S REAL ESTATE L.L.C · Saih Shuaib 2 · 163 units

declared value 37.0M AED data last checked 12 Sept 2026

B+G+5+ROOF

Construction progress

0% of construction complete · last inspected by DLD 20 Aug 2025

on pace with the planned timeline

last DLD inspection was 1.1 years ago — this figure may no longer reflect the site's actual progress

today inspected 20 Aug 2025
start 30 Sept 2025 est. finish 30 Nov 2027
Google · this project
5.0
3 reviews