City Walk Crestlane 1photo: meraas.comActive
Progress
0.19%
Handover
~ Sept 2029
Escrow
#0323556074002

City Walk Crestlane 1

#3801 · CITYWALK RESIDENTIAL 1 L.L.C · Al Wasl

More from Meraas
data last checked 17 Jul 2026

Construction progress

0.19% of construction complete · last inspected by DLD 3 Aug 2026

on pace — ≈22 pts behind the plan as of the last inspection

today
inspected 3 Aug 2026
start 8 Sept 2025 est. finish 30 Sept 2029