photo: darglobal.co.ukDelayedCity Center Residences
DLD developer no. 1221 · DAR GLOBAL PROPERTIES L.L.C
Data last checked 29 Oct 2026
Tower consists of 1B+G+4P+49F+1MECH+R+4UR Floors (Residential Commercial) with external and internal finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 15 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 70.42 | 758 | 2,000,000 | 28,401 | 2,639 |
| 13 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 70.32 | 757 | 2,050,000 | 29,152 | 2,708 |
| 24 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 109.99 | 1,184 | 2,393,505.6 | 21,761 | 2,022 |
| 23 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 134.79 | 1,451 | 5,600,000 | 41,546 | 3,860 |
| 8 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 134.57 | 1,448 | 4,550,000 | 33,811 | 3,141 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.14 | 777 | 2,100,000 | 29,110 | 2,704 |
| 3 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 70.34 | 757 | 1,706,562 | 24,262 | 2,254 |
| 29 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 73.33 | 789 | 1,600,000 | 21,819 | 2,027 |
| 15 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 70.38 | 758 | 1,955,023 | 27,778 | 2,581 |
| 10 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 99.62 | 1,072 | 2,350,000 | 23,590 | 2,192 |
| 7 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 73 | 786 | 1,616,908 | 22,149 | 2,058 |
| 6 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 109.74 | 1,181 | 3,750,000 | 34,172 | 3,175 |
| 28 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 72.99 | 786 | 1,675,000 | 22,948 | 2,132 |
| 18 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 73.29 | 789 | 1,607,583 | 21,935 | 2,038 |
| 17 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 73.08 | 787 | 1,854,023 | 25,370 | 2,357 |
City Center Residences: common questions
Is City Center Residences delayed?
It is behind plan. Construction was 72.3% complete at the last DLD inspection on 10 September 2026, while its registered timeline (planned completion 30 September 2026) would expect about 99% by then.
When is the handover of City Center Residences?
The planned completion date registered with Dubai Land Department is 30 September 2026. Handover usually follows completion; the developer confirms the exact date.
How much of City Center Residences is built?
Construction was 72.3% complete at the last DLD inspection on 10 September 2026, as published by Dubai Land Department.
Where is City Center Residences located?
City Center Residences is in Burj Khalifa, Dubai.
Who is the developer of City Center Residences?
City Center Residences is developed by DAR GLOBAL PROPERTIES L.L.C (DLD developer no. 1221). It is registered with Dubai Land Department as project no. 2359, with 397 units.
Does City Center Residences have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205840270707. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in City Center Residences?
The most recent sale registered with Dubai Land Department was on 15 October 2026 for AED 2,000,000. Across the 24 recorded sales, the average was AED 2,681 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.