photo: damacproperties.comUnder constructionDeveloper: Damac Crest Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Damac →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 190.02 | 2,045 | 5,690,000 | 29,944 | 2,782 |
| 23 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 93.04 | 1,001 | 3,132,000 | 33,663 | 3,127 |
| 30 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 71.94 | 774 | 2,510,640 | 34,899 | 3,242 |
| 25 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 85.57 | 921 | 2,949,210 | 34,465 | 3,202 |
| 22 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 154.16 | 1,659 | 4,955,040 | 32,142 | 2,986 |
| 11 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 71.94 | 774 | 2,406,350 | 33,449 | 3,108 |
| 26 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 85.57 | 921 | 2,961,000 | 34,603 | 3,215 |
| 21 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 72.17 | 777 | 2,416,800 | 33,488 | 3,111 |
| 21 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 107.58 | 1,158 | 3,439,680 | 31,973 | 2,970 |
| 11 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 85.57 | 921 | 2,992,000 | 34,966 | 3,248 |
| 10 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 83.02 | 894 | 3,046,000 | 36,690 | 3,409 |
| 6 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 72.12 | 776 | 2,518,000 | 34,914 | 3,244 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 85.57 | 921 | 2,985,000 | 34,884 | 3,241 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 154.47 | 1,663 | 4,999,000 | 32,362 | 3,007 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 93 | 1,001 | 2,912,720 | 31,320 | 2,910 |
CHELSEA RESIDENCES 2 BY DAMAC: common questions
Is CHELSEA RESIDENCES 2 BY DAMAC delayed?
Not by DLD figures. Construction was 5.44% complete at the last DLD inspection on 6 August 2026, in line with or ahead of its registered timeline (about 20% expected by then, planned completion 31 December 2029).
When is the handover of CHELSEA RESIDENCES 2 BY DAMAC?
The planned completion date registered with Dubai Land Department is 31 December 2029. Handover usually follows completion; the developer confirms the exact date.
How much of CHELSEA RESIDENCES 2 BY DAMAC is built?
Construction was 5.44% complete at the last DLD inspection on 6 August 2026, as published by Dubai Land Department.
Where is CHELSEA RESIDENCES 2 BY DAMAC located?
CHELSEA RESIDENCES 2 BY DAMAC is in Dubai Maritime City, Dubai.
Who is the developer of CHELSEA RESIDENCES 2 BY DAMAC?
CHELSEA RESIDENCES 2 BY DAMAC is developed by Damac Crest Development L.L.C. It is registered with Dubai Land Department as project no. 3743.
Does CHELSEA RESIDENCES 2 BY DAMAC have an escrow account?
Yes. Dubai Land Department open data lists escrow account 14196956920001. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in CHELSEA RESIDENCES 2 BY DAMAC?
The most recent sale registered with Dubai Land Department was on 26 October 2026 for AED 5,690,000. Across the 142 recorded sales, the average was AED 3,191 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.