CG Livingphoto: cg-developers.comUnder construction

CG Living

DLD project no. 4060 · Palm Deira

Progress
1.57%
DLD inspected 18 May 2026
Handover
~ Jun 2028
Est. finish 30 Jun 2028
Escrow
#200881559
Registered escrow account
Google rating
—

Developer: C G Gulf Real Estate Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
1.57% of construction complete · last inspected by DLD 18 May 2026

≈28 pts behind the planned pace as of the last inspection

today
inspected 18 May 2026
start 30 Jun 2025 est. finish 30 Jun 2028

CG Living: common questions

Is CG Living delayed?

It is behind plan. Construction was 1.57% complete at the last DLD inspection on 18 May 2026, while its registered timeline (planned completion 30 June 2028) would expect about 29% by then.

When is the handover of CG Living?

The planned completion date registered with Dubai Land Department is 30 June 2028. Handover usually follows completion; the developer confirms the exact date.

How much of CG Living is built?

Construction was 1.57% complete at the last DLD inspection on 18 May 2026, as published by Dubai Land Department.

Where is CG Living located?

CG Living is in Palm Deira, Dubai.

Who is the developer of CG Living?

CG Living is developed by C G Gulf Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 4060.

Does CG Living have an escrow account?

Yes. Dubai Land Department open data lists escrow account 200881559. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in CG Living?

The most recent sale registered with Dubai Land Department was on 13 July 2026 for AED 5,749,000. Across the 22 recorded sales, the average was AED 3,887 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.