Under construction

CETARA

DLD project no. 4382 · Al Hebiah Fifth · 682 units

Progress
0.25%
DLD inspected 8 Sept 2026
Handover
~ Jan 2030
Est. finish 31 Jan 2030
Escrow
#498067920010
Registered escrow account
Google rating
—

DLD developer no. 921 · ISLAND OASIS PROPERTIES

Data last checked 29 Oct 2026

More from Damac →
declared value 311.5M AED

Project consists of 4 Residential towers of G+3P+16+R floors. it is designed to have concrete structure and block with internal and external finishes.

DLDConstruction inspection
0.25% of construction complete · last inspected by DLD 8 Sept 2026

on pace — ≈4 pts behind the plan as of the last inspection

today
inspected 8 Sept 2026
start 15 Jul 2026 est. finish 31 Jan 2030
Earlier inspections4 Sept 2026 · 0.25%2 Feb 2026 · 0%

CETARA: common questions

Is CETARA delayed?

Not by DLD figures. Construction was 0.25% complete at the last DLD inspection on 8 September 2026, in line with or ahead of its registered timeline (about 4% expected by then, planned completion 31 January 2030).

When is the handover of CETARA?

The planned completion date registered with Dubai Land Department is 31 January 2030. Handover usually follows completion; the developer confirms the exact date.

How much of CETARA is built?

Construction was 0.25% complete at the last DLD inspection on 8 September 2026, as published by Dubai Land Department.

Where is CETARA located?

CETARA is in Al Hebiah Fifth, Dubai.

Who is the developer of CETARA?

CETARA is developed by ISLAND OASIS PROPERTIES (DLD developer no. 921). It is registered with Dubai Land Department as project no. 4382, with 682 units.

Does CETARA have an escrow account?

Yes. Dubai Land Department open data lists escrow account 498067920010. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.