photo: tarrad.aeUnder constructionCelesto Tower
DLD developer no. 1921 · TARRAD DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 16 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 72.82 | 784 | 918,995 | 12,620 | 1,172 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 57.23 | 616 | 819,574 | 14,321 | 1,330 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 86.43 | 930 | 1,198,870 | 13,871 | 1,289 |
| 14 Sept 2026 | Sales | Off-plan | Flat · Studio | 33.95 | 365 | 550,000 | 16,200 | 1,505 |
| 4 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 66.11 | 712 | 926,966 | 14,022 | 1,303 |
| 31 Aug 2026 | Sales | Off-plan | Flat · Studio | 48.23 | 519 | 652,800 | 13,535 | 1,257 |
| 22 Aug 2026 | Sales | Off-plan | Flat · Studio | 36.66 | 395 | 587,370 | 16,022 | 1,489 |
| 11 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 66.11 | 712 | 981,225 | 14,842 | 1,379 |
| 10 Aug 2026 | Sales | Off-plan | Flat · Studio | 33.18 | 357 | 542,864 | 16,361 | 1,520 |
| 5 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 57.14 | 615 | 743,404 | 13,010 | 1,209 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 57.23 | 616 | 803,183 | 14,034 | 1,304 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 57.23 | 616 | 842,688 | 14,725 | 1,368 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 67.89 | 731 | 834,730 | 12,295 | 1,142 |
| 28 Jul 2026 | Sales | Off-plan | Flat · Studio | 33.05 | 356 | 542,435 | 16,413 | 1,525 |
| 25 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 77.84 | 838 | 938,636 | 12,059 | 1,120 |
Celesto Tower: common questions
Is Celesto Tower delayed?
It is behind plan. Construction was 3.89% complete at the last DLD inspection on 18 June 2026, while its registered timeline (planned completion 31 December 2027) would expect about 29% by then.
When is the handover of Celesto Tower?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Celesto Tower is built?
Construction was 3.89% complete at the last DLD inspection on 18 June 2026, as published by Dubai Land Department.
Where is Celesto Tower located?
Celesto Tower is in Dubai Land Residence Complex, Dubai.
Who is the developer of Celesto Tower?
Celesto Tower is developed by TARRAD DEVELOPMENT L.L.C (DLD developer no. 1921). It is registered with Dubai Land Department as project no. 4106.
Does Celesto Tower have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019500000830. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Celesto Tower?
The most recent sale registered with Dubai Land Department was on 16 October 2026 for AED 918,995. Across the 119 recorded sales, the average was AED 1,401 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.