photo: hredevelopment.comUnder constructionCeleste
DLD developer no. 1669 · HRE REAL ESTATE DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 12 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 87.77 | 945 | 2,024,190 | 23,062 | 2,143 |
| 18 Jul 2026 | Sales | Off-plan | Shop · NA | 49.25 | 530 | 2,075,000 | 42,132 | 3,914 |
| 11 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 70.02 | 754 | 1,752,305 | 25,026 | 2,325 |
| 6 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 74.7 | 804 | 1,707,650 | 22,860 | 2,124 |
| 27 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 70.02 | 754 | 1,707,650 | 24,388 | 2,266 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 87.77 | 945 | 1,890,000 | 21,534 | 2,001 |
| 14 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 128.67 | 1,385 | 2,406,240 | 18,701 | 1,737 |
| 13 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 86.36 | 930 | 1,943,000 | 22,499 | 2,090 |
| 13 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 137.57 | 1,481 | 2,864,640 | 20,823 | 1,935 |
| 13 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.7 | 804 | 1,719,410 | 23,018 | 2,138 |
| 16 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 86.36 | 930 | 1,973,720 | 22,855 | 2,123 |
| 16 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 99.71 | 1,073 | 2,479,000 | 24,862 | 2,310 |
| 16 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 86.36 | 930 | 2,019,500 | 23,385 | 2,173 |
| 16 Feb 2026 | Sales | Off-plan | Flat · 2 B/R | 87.77 | 945 | 1,904,500 | 21,699 | 2,016 |
| 26 Jan 2026 | Sales | Off-plan | Flat · 2 B/R | 86.36 | 930 | 1,935,500 | 22,412 | 2,082 |
Celeste: common questions
Is Celeste delayed?
It is behind plan. Construction was 3% complete at the last DLD inspection on 30 July 2026, while its registered timeline (planned completion 28 February 2027) would expect about 72% by then.
When is the handover of Celeste?
The planned completion date registered with Dubai Land Department is 28 February 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Celeste is built?
Construction was 3% complete at the last DLD inspection on 30 July 2026, as published by Dubai Land Department.
Where is Celeste located?
Celeste is in Jaddaf Waterfront, Dubai.
Who is the developer of Celeste?
Celeste is developed by HRE REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1669). It is registered with Dubai Land Department as project no. 3527.
Does Celeste have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0012157179009. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Celeste?
The most recent sale registered with Dubai Land Department was on 12 September 2026 for AED 2,024,190. Across the 21 recorded sales, the average was AED 2,362 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.