Casa Aura Residencephoto: agnskyline.comUnder construction

Casa Aura Residence

DLD project no. 3522 · Dubai South

Progress
6.32%
DLD inspected 4 May 2026
Handover
~ Sept 2027
Est. finish 12 Sept 2027
Escrow
#200847931
Registered escrow account
Google rating
—

Developer: A G N Skyline Real Estate Developments L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
6.32% of construction complete · last inspected by DLD 4 May 2026

≈36 pts behind the planned pace as of the last inspection

today
inspected 4 May 2026
start 12 May 2025 est. finish 12 Sept 2027

Location

Casa Aura Residence: common questions

Is Casa Aura Residence delayed?

It is behind plan. Construction was 6.32% complete at the last DLD inspection on 4 May 2026, while its registered timeline (planned completion 12 September 2027) would expect about 42% by then.

When is the handover of Casa Aura Residence?

The planned completion date registered with Dubai Land Department is 12 September 2027. Handover usually follows completion; the developer confirms the exact date.

How much of Casa Aura Residence is built?

Construction was 6.32% complete at the last DLD inspection on 4 May 2026, as published by Dubai Land Department.

Where is Casa Aura Residence located?

Casa Aura Residence is in Dubai South, Dubai.

Who is the developer of Casa Aura Residence?

Casa Aura Residence is developed by A G N Skyline Real Estate Developments L.L.C. It is registered with Dubai Land Department as project no. 3522.

Does Casa Aura Residence have an escrow account?

Yes. Dubai Land Department open data lists escrow account 200847931. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Casa Aura Residence?

The most recent sale registered with Dubai Land Department was on 30 June 2026 for AED 1,361,282. Across the 6 recorded sales, the average was AED 1,327 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.