CASA AHSphoto: ahsproperties.comUnder construction

CASA AHS

DLD project no. 3589 · Dubai Water Canal

Progress
16.06%
DLD inspected 24 Sept 2026
Handover
~ May 2027
Est. finish 31 May 2027
Escrow
#14040066920002
Registered escrow account
Google rating
5.0 ★
5 reviews

Developer: Ahs Canal Three Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
16.06% of construction complete · last inspected by DLD 24 Sept 2026

≈50 pts behind the planned pace as of the last inspection

today
inspected 24 Sept 2026
start 1 Jun 2025 est. finish 31 May 2027
Google · this project
5.0
5 reviews

Location

CASA AHS: common questions

Is CASA AHS delayed?

It is behind plan. Construction was 16.06% complete at the last DLD inspection on 24 September 2026, while its registered timeline (planned completion 31 May 2027) would expect about 66% by then.

When is the handover of CASA AHS?

The planned completion date registered with Dubai Land Department is 31 May 2027. Handover usually follows completion; the developer confirms the exact date.

How much of CASA AHS is built?

Construction was 16.06% complete at the last DLD inspection on 24 September 2026, as published by Dubai Land Department.

Where is CASA AHS located?

CASA AHS is in Dubai Water Canal, Dubai.

Who is the developer of CASA AHS?

CASA AHS is developed by Ahs Canal Three Development L.L.C. It is registered with Dubai Land Department as project no. 3589.

Does CASA AHS have an escrow account?

Yes. Dubai Land Department open data lists escrow account 14040066920002. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in CASA AHS?

The most recent sale registered with Dubai Land Department was on 5 May 2026 for AED 46,000,000. Across the 11 recorded sales, the average was AED 4,527 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.