CAPRIA EASTphoto: ghafwoods.comUnder construction

CAPRIA EAST

DLD project no. 3524 · Wadi Al Safa 4

Progress
0.94%
DLD inspected 23 Jun 2026
Handover
~ May 2029
Est. finish 15 May 2029
Escrow
#0205872406711
Registered escrow account
Google rating
—

Developer: Majid Al Futtaim Ghaf Woods L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Majid Al Futtaim →
DLDConstruction inspection
0.94% of construction complete · last inspected by DLD 23 Jun 2026

on pace — ≈20 pts behind the plan as of the last inspection

today
inspected 23 Jun 2026
start 15 Sept 2025 est. finish 15 May 2029
Google · this project
0 reviews

CAPRIA EAST: common questions

Is CAPRIA EAST delayed?

Not by DLD figures. Construction was 0.94% complete at the last DLD inspection on 23 June 2026, in line with or ahead of its registered timeline (about 21% expected by then, planned completion 15 May 2029).

When is the handover of CAPRIA EAST?

The planned completion date registered with Dubai Land Department is 15 May 2029. Handover usually follows completion; the developer confirms the exact date.

How much of CAPRIA EAST is built?

Construction was 0.94% complete at the last DLD inspection on 23 June 2026, as published by Dubai Land Department.

Where is CAPRIA EAST located?

CAPRIA EAST is in Wadi Al Safa 4, Dubai.

Who is the developer of CAPRIA EAST?

CAPRIA EAST is developed by Majid Al Futtaim Ghaf Woods L.L.C. It is registered with Dubai Land Department as project no. 3524.

Does CAPRIA EAST have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0205872406711. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in CAPRIA EAST?

The most recent sale registered with Dubai Land Department was on 30 July 2026 for AED 6,131,000. Across the 47 recorded sales, the average was AED 2,271 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.