photo: capitalone-dubai.comUnder constructionCapital One
Developer: The Circuit Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Gifts | Off-plan | Office · Office | 88.07 | 948 | 1,700,676.12 | 19,311 | 1,794 |
| 29 Sept 2026 | Sales | Off-plan | Office · Office | 74.21 | 799 | 1,336,688 | 18,012 | 1,673 |
| 29 Sept 2026 | Sales | Off-plan | Office · Office | 133.46 | 1,437 | 2,425,048 | 18,171 | 1,688 |
| 16 Sept 2026 | Sales | Off-plan | Office · Office | 88.12 | 949 | 1,571,468 | 17,833 | 1,657 |
| 16 Sept 2026 | Sales | Off-plan | Office · Office | 165.14 | 1,778 | 3,028,378 | 18,338 | 1,704 |
| 16 Sept 2026 | Sales | Off-plan | Office · Office | 88.12 | 949 | 1,601,498 | 18,174 | 1,688 |
| 16 Sept 2026 | Sales | Off-plan | Office · Office | 167.69 | 1,805 | 3,072,968 | 18,325 | 1,702 |
| 2 Sept 2026 | Sales | Off-plan | Office · Office | 132.83 | 1,430 | 2,872,196 | 21,623 | 2,009 |
| 15 Aug 2026 | Sales | Off-plan | Office · Office | 80.08 | 862 | 2,068,888 | 25,835 | 2,400 |
| 13 Aug 2026 | Sales | Off-plan | Shop · Shop | 203.48 | 2,190 | 2,100,000 | 10,320 | 959 |
| 30 Jul 2026 | Sales | Off-plan | Office · Office | 153.4 | 1,651 | 2,572,141 | 16,768 | 1,558 |
| 23 May 2026 | Sales | Off-plan | Office · Office | 88.07 | 948 | 2,075,000 | 23,561 | 2,189 |
| 11 May 2026 | Sales | Off-plan | Office · Office | 171.91 | 1,850 | 3,343,474 | 19,449 | 1,807 |
| 22 Apr 2026 | Sales | Off-plan | Office · Office | 197.42 | 2,125 | 3,587,874 | 18,174 | 1,688 |
| 14 Apr 2026 | Sales | Off-plan | Office · Office | 171.22 | 1,843 | 3,521,656 | 20,568 | 1,911 |
Capital One: common questions
Is Capital One delayed?
It is behind plan. Construction was 20.02% complete at the last DLD inspection on 8 October 2026, while its registered timeline (planned completion 9 February 2027) would expect about 85% by then.
When is the handover of Capital One?
The planned completion date registered with Dubai Land Department is 9 February 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Capital One is built?
Construction was 20.02% complete at the last DLD inspection on 8 October 2026, as published by Dubai Land Department.
Where is Capital One located?
Capital One is in Motor City, Dubai.
Who is the developer of Capital One?
Capital One is developed by The Circuit Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3407.
Does Capital One have an escrow account?
Yes. Dubai Land Department open data lists escrow account 13955377920003. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Capital One?
The most recent sale registered with Dubai Land Department was on 29 September 2026 for AED 1,336,688. Across the 42 recorded sales, the average was AED 1,819 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.