CANAL CROWN 2photo: damacproperties.comUnder construction

CANAL CROWN 2

DLD project no. 2626 · Business Bay

Progress
32.53%
DLD inspected 8 Sept 2026
Handover
~ Mar 2027
Est. finish 31 Mar 2027
Escrow
#28857671
Registered escrow account
Google rating
4.5 ★
10 reviews

Developer: One Quantem Real Estate Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Damac →
DLDConstruction inspection
32.53% of construction complete · last inspected by DLD 8 Sept 2026

≈52 pts behind the planned pace as of the last inspection

today
inspected 8 Sept 2026
start 8 Aug 2023 est. finish 31 Mar 2027
Google · this project
4.5
10 reviews

Location

CANAL CROWN 2: common questions

Is CANAL CROWN 2 delayed?

It is behind plan. Construction was 32.53% complete at the last DLD inspection on 8 September 2026, while its registered timeline (planned completion 31 March 2027) would expect about 85% by then.

When is the handover of CANAL CROWN 2?

The planned completion date registered with Dubai Land Department is 31 March 2027. Handover usually follows completion; the developer confirms the exact date.

How much of CANAL CROWN 2 is built?

Construction was 32.53% complete at the last DLD inspection on 8 September 2026, as published by Dubai Land Department.

Where is CANAL CROWN 2 located?

CANAL CROWN 2 is in Business Bay, Dubai.

Who is the developer of CANAL CROWN 2?

CANAL CROWN 2 is developed by One Quantem Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 2626.

Does CANAL CROWN 2 have an escrow account?

Yes. Dubai Land Department open data lists escrow account 28857671. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in CANAL CROWN 2?

The most recent sale registered with Dubai Land Department was on 14 October 2026 for AED 2,933,920. Across the 10 recorded sales, the average was AED 2,761 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.