CANAL CROWNphoto: damacproperties.comUnder construction

CANAL CROWN

DLD project no. 2625 · Business Bay

Progress
42.15%
DLD inspected 15 Jul 2026
Handover
~ Feb 2027
Est. finish 28 Feb 2027
Escrow
#28853404
Registered escrow account
Google rating
4.5 ★
10 reviews

Developer: Galaxy Sky Real Estate Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Damac →
DLDConstruction inspection
42.15% of construction complete · last inspected by DLD 15 Jul 2026

≈40 pts behind the planned pace as of the last inspection

today
inspected 15 Jul 2026
start 1 Aug 2023 est. finish 28 Feb 2027
Google · this project
4.5
10 reviews

Location

CANAL CROWN: common questions

Is CANAL CROWN delayed?

It is behind plan. Construction was 42.15% complete at the last DLD inspection on 15 July 2026, while its registered timeline (planned completion 28 February 2027) would expect about 83% by then.

When is the handover of CANAL CROWN?

The planned completion date registered with Dubai Land Department is 28 February 2027. Handover usually follows completion; the developer confirms the exact date.

How much of CANAL CROWN is built?

Construction was 42.15% complete at the last DLD inspection on 15 July 2026, as published by Dubai Land Department.

Where is CANAL CROWN located?

CANAL CROWN is in Business Bay, Dubai.

Who is the developer of CANAL CROWN?

CANAL CROWN is developed by Galaxy Sky Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 2625.

Does CANAL CROWN have an escrow account?

Yes. Dubai Land Department open data lists escrow account 28853404. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in CANAL CROWN?

The most recent sale registered with Dubai Land Department was on 11 September 2026 for AED 2,388,000. Across the 13 recorded sales, the average was AED 2,803 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.