photo: centurionproperties.aeUnder constructionburj capital
Developer: Centurion Capital One Properties L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Sales | Off-plan | Office · NA | 143.16 | 1,541 | 5,734,000 | 40,053 | 3,721 |
| 22 Oct 2026 | Sales | Off-plan | Office · NA | 141.02 | 1,518 | 5,161,100 | 36,598 | 3,400 |
| 19 Oct 2026 | Sales | Off-plan | Office · NA | 78.1 | 841 | 2,824,400 | 36,164 | 3,360 |
| 17 Oct 2026 | Sales | Off-plan | Office · NA | 141.04 | 1,518 | 5,022,750 | 35,612 | 3,308 |
| 17 Oct 2026 | Sales | Off-plan | Office · NA | 68.92 | 742 | 2,509,800 | 36,416 | 3,383 |
| 16 Oct 2026 | Sales | Off-plan | Office · NA | 70.5 | 759 | 3,929,200 | 55,733 | 5,178 |
| 9 Oct 2026 | Sales | Off-plan | Office · NA | 141.04 | 1,518 | 5,412,000 | 38,372 | 3,565 |
| 30 Sept 2026 | Sales | Off-plan | Office · NA | 141.01 | 1,518 | 4,585,000 | 32,515 | 3,021 |
| 30 Sept 2026 | Sales | Off-plan | Office · NA | 68.92 | 742 | 2,520,000 | 36,564 | 3,397 |
| 21 Sept 2026 | Sales | Off-plan | Office · NA | 70.49 | 759 | 2,934,800 | 41,634 | 3,868 |
| 16 Sept 2026 | Sales | Off-plan | Office · NA | 70.49 | 759 | 2,741,200 | 38,888 | 3,613 |
| 16 Sept 2026 | Sales | Off-plan | Office · NA | 70.48 | 759 | 3,102,500 | 44,020 | 4,090 |
| 5 Sept 2026 | Sales | Off-plan | Office · NA | 78.1 | 841 | 2,880,000 | 36,876 | 3,426 |
| 26 Aug 2026 | Sales | Off-plan | Office · NA | 141.03 | 1,518 | 5,080,800 | 36,026 | 3,347 |
| 23 Aug 2026 | Sales | Off-plan | Office · NA | 78.09 | 841 | 2,664,000 | 34,114 | 3,169 |
burj capital: common questions
Is burj capital delayed?
It is behind plan. Construction was 1.5% complete at the last DLD inspection on 28 July 2026, while its registered timeline (planned completion 22 December 2028) would expect about 31% by then.
When is the handover of burj capital?
The planned completion date registered with Dubai Land Department is 22 December 2028. Handover usually follows completion; the developer confirms the exact date.
How much of burj capital is built?
Construction was 1.5% complete at the last DLD inspection on 28 July 2026, as published by Dubai Land Department.
Where is burj capital located?
burj capital is in Business Bay, Dubai.
Who is the developer of burj capital?
burj capital is developed by Centurion Capital One Properties L.L.C. It is registered with Dubai Land Department as project no. 3659.
Does burj capital have an escrow account?
Yes. Dubai Land Department open data lists escrow account 80260600000014. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in burj capital?
The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 5,734,000. Across the 99 recorded sales, the average was AED 3,713 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.