photo: jre.aeDelayed 3 mo.BRAND CENTRO
DLD developer no. 1820 · E M S REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
Residential Building 1: G+2P+8F+R
Location
This project on Google
Sale register covers the last ~3 months.
No sales match this filter in the stored window.
BRAND CENTRO: common questions
Is BRAND CENTRO delayed?
Not by DLD figures. Construction was 90.02% complete at the last DLD inspection on 28 July 2026, in line with or ahead of its registered timeline (about 100% expected by then, planned completion 30 July 2026).
When is the handover of BRAND CENTRO?
The planned completion date registered with Dubai Land Department is 30 July 2026. Handover usually follows completion; the developer confirms the exact date.
How much of BRAND CENTRO is built?
Construction was 90.02% complete at the last DLD inspection on 28 July 2026, as published by Dubai Land Department.
Where is BRAND CENTRO located?
BRAND CENTRO is in Al Satwa, Dubai.
Who is the developer of BRAND CENTRO?
BRAND CENTRO is developed by E M S REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1820). It is registered with Dubai Land Department as project no. 3235, with 56 units.
Does BRAND CENTRO have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205889589503. Always confirm the account with the developer or in the Dubai REST app before paying.
Answers are generated from Dubai Land Department open data shown on this page.