Active
Progress
30.04%
Handover
~ Jul 2027
Escrow
#0205946514503

Bottega Nove by Lalav

#4324 · BOTTEGA NOVE BY LALAV REAL ESTATE DEVELOPMENT L.L.C · Wadi Al Safa 3 · 60 units

declared value 63.9M AED data last checked 12 Sept 2026

Residential and Commercial Building G+P+9FLRS+ROOF

Construction progress

30.04% of construction complete · last inspected by DLD 12 Aug 2026

≈28 pts behind the planned pace as of the last inspection

today
inspected 12 Aug 2026
start 4 Apr 2025 est. finish 30 Jul 2027